1. |
What is the duty cycle for a spot welder supplied by a 60-Hz system (216,000 cycles per hour) making three hundred 15-cycle welds per hour?
|
|
|
|
|
|
a)
|
1percent
|
|
b)
|
2.1 percent
|
|
c)
|
3.2 percent
|
|
|
|
|
|
|
2. |
In general, where installed in raceways conductors larger than No. _____shall be stranded.
|
|
|
|
|
|
a)
|
8
|
|
b)
|
10
|
|
c)
|
6
|
|
d)
|
4
|
|
|
|
|
|
|
3. |
With a feeder load of 14 kW on a household electric range, the maximum unbalanced load shall be considered to carry a load of : (chose the closest answer)
|
|
|
|
|
|
a)
|
41 amperes
|
|
b)
|
26 amperes
|
|
c)
|
33 amperes
|
|
|
|
|
|
|
4. |
Where THHN conductors are added to an existing raceway that contains older 60 degree C insulated conductors, the ampacity of the THHN conductors cannot exceed _______.
|
|
|
|
|
|
a)
|
The ampacities in the 60 degree column
|
|
b)
|
The ampacities in the 75 degree column
|
|
c)
|
The ampacities in the 90 degree column
|
|
d)
|
The ampacities in the 90 degree column with 60 percent derating.
|
|
|
|
|
|
|
5. |
The ampacity of a 75 degree C. rated conductor in an ambient of 75 degrees C. is ____.
|
|
|
|
|
|
a)
|
0 amperes
|
|
b)
|
90 percent of its normal ampacity
|
|
c)
|
60 percent of its 75 degree ampacity
|
|
|
|
|
|
|
6. |
Wiring to receptacles under raised floors in computer rooms shall be ______.
|
|
|
|
|
|
a)
|
Type MI cable, Type MC cable, or Type AC cable
|
|
b)
|
In rigid metal conduit, rigid nonmetallic conduit, intermediate metal conduit, electrical metallic tubing, metal wireway, surface metal raceway with metal cover, flexible metal conduit, liquidtight flexible metal or nonmetallic conduit
|
|
c)
|
Nonmetallic Shielded Cable (NMB)
|
|
d)
|
All of the above
|
|
e)
|
A or B of the above
|
|
|
|
|
|
|
7. |
Intrinsically safe circuits can be identified using ______.
|
|
|
|
|
|
a)
|
blue color
|
|
b)
|
red color
|
|
c)
|
orange color
|
|
d)
|
any color
|
|
|
|
|
|
|
8. |
Nonincenditive circuits shall be permitted to be used in ______areas.
|
|
|
|
|
|
a)
|
Class I, Division 2
|
|
b)
|
Class I, Division 1
|
|
c)
|
Class III
|
|
d)
|
All of the above
|
|
e)
|
Only a and c.
|
|
|
|
|
|
|
9. |
What is the maximum distance allowed for spacing supports for No. 10 copper conductors which are vertically installed in raceways.
|
|
|
|
|
|
a)
|
25 feet
|
|
b)
|
50 feet
|
|
c)
|
100 feet
|
|
d)
|
150 feet
|
|
|
|
|
|
|
10. |
Flat conductor cable installations:
|
|
|
|
|
|
a)
|
Are suitable for school installations
|
|
b)
|
Must be installed under carpet squares
|
|
c)
|
Can only be installed on concrete floors
|
|
d)
|
Are limited to voltages not exceeding 150 volts.
|
|
|
|
|
|
|
11. |
A restaurant may be wired using nonmetallic sheathed cable when:
(1) The building is NOT required to be fire rated construction.
(2) The building does not exceed 3 floors and the restaurant occupancy load is less than 100 persons.
(Select the best answer.)
|
|
|
|
|
|
a)
|
1 only
|
|
b)
|
2 only
|
|
c)
|
Both 1 and 2
|
|
d)
|
Neither 1 or 2
|
|
|
|
|
|
|
12. |
Mineral insulated cable is approved for almost all locations and conditions but one of the below. Which is it?`
|
|
|
|
|
|
a)
|
Where embedded in concrete
|
|
b)
|
Exposed to gasoline
|
|
c)
|
where exposed to destructive corrosive conditions
|
|
|
|
|
|
|
13. |
Type AC cable shall be constructed to include:
|
|
|
|
|
|
a)
|
At least 3 conductors
|
|
b)
|
An insulated equipment grounding conductor
|
|
c)
|
An internal bonding strip of copper or aluminum in intimate contact with the armor for its entire length.
|
|
|
|
|
|
|
14. |
The pull box below is used for conductors larger than No. 6. What are the required minimum dimensions for X and Y?
|
|
|
|
|
|
a)
|
X = 24 inches, Y = 16 inches
|
|
b)
|
X = 20 inches, Y = 24 inches
|
|
c)
|
X = 24 inches, Y = 24 inches
|
|
d)
|
X = 30 inches, Y = 30 inches
|
|
|
|
|
|
|
15. |
How many 1/2 inch diameter control cables can be installed in a 18 inch ladder type cable tray with 6 inch high sides?
|
|
|
|
|
|
a)
|
100
|
|
b)
|
125
|
|
c)
|
150
|
|
d)
|
275
|
|
|
|
|
|
|
16. |
If a service consists of 4 each 500 kcmil copper conductors per phase in a gutter and is 3 -phase 4 wire 480/277 volts what size copper bonding jumper is required on the supply side of the service disconnecting means?
|
|
|
|
|
|
a)
|
3/0
|
|
b)
|
250 kcmil
|
|
c)
|
300 kcmil
|
|
d)
|
350 kcmil
|
|
|
|
|
|
|
17. |
Disregarding exceptions the minimum cover requirement for a direct burial cable with a circuit voltage of 7200 volts to ground is _______.
|
|
|
|
|
|
a)
|
30 inches
|
|
b)
|
36 inches
|
|
c)
|
42 inches
|
|
d)
|
48 inches
|
|
|
|
|
|
|
18. |
When is ground fault protection required on a service?
|
|
|
|
|
|
a)
|
277/480 volts solidly grounded Wye rated at 1000 amperes or more
|
|
b)
|
120/208 volts Wye rated 1200 amperes or more
|
|
c)
|
120/240 volts rated 1000 amperes or more
|
|
d)
|
All of the above
|
|
|
|
|
|
|
19. |
How many three way and four way switches are required to operate a light from eight (8) locations?
|
|
|
|
|
|
a)
|
6 each 3 way, and 2 each 4 way
|
|
b)
|
2 each 3 way and 6 each 4 way
|
|
c)
|
3 each 3 way and 3 each 4 way
|
|
d)
|
None of the above - it cannot be done.
|
|
|
|
|
|
|
20. |
When does the Code allow welding of Conduit or couplings?
|
|
|
|
|
|
a)
|
Where raceway risers or cable is not installed within the (lighting) pole, a threaded fitting or nipple shall be brazed or welded to the pole opposite the handhole for the supply connection.
|
|
b)
|
The Code does not allow welding of conduit.
|
|
c)
|
Conduit couplings can always be welded
|
|
d)
|
Conduit can be welded when the AHJ allows it.
|
|
e)
|
a and d
|
|
|
|
|
|
|